District Spends $5 Million on Road & Sewer Work

Posted: 2018-06-22 07:48:48 By: hbr

District council signed off on several projects Monday night worth a grand total of more than $5 million.

A large portion of the funding - some $2.1 million will be used for the replacement of the existing storm sewer in MacTier. That same project is expected to run now through November of 2018. It is also expected to result in a full road closure of Muskoka Road #11 (High Street) from now until July 20.

Another $2.5 million was allocated for road repairs to various District roads throughout the region.